A phased, practical IT relocation checklist built from hundreds of office moves. Follow it week by week and your team will walk into a working office — not a room full of unplugged boxes.
Most parts of an office move can be compressed into a single weekend. One thing cannot.
Ask anyone who has managed an office relocation and they will tell you the same story: the desks arrived, the servers arrived, the staff arrived — and the internet did not. New connectivity lead times are the single biggest cause of delayed IT relocations in the UK. A new fibre leased line can take 30 to 90 working days to install, and even a standard broadband or FTTP circuit typically needs two to four weeks. If the new premises need construction work for the fibre entry, add more.
Before you book removal vans, before you order furniture, before almost anything else: place the order for connectivity at the new site. Confirm what circuits already exist in the building, order the new line, and arrange a 4G/5G or broadband backup as a contingency in case the install date slips. Everything else in this checklist assumes you have done this on day one.
This is the planning phase. The work you do now determines whether move weekend is calm or chaotic.
Preparation shifts from paper to premises. The new site should start becoming IT-ready now.
Confirm full backups of every server and critical system are running and completing successfully. Check retention, check the backup destination is off-site or in the cloud, and log in to the backup console yourself rather than assuming. If disaster strikes in transit, this is your safety net.
Commission a structured cabling survey of the new premises. Count data points per desk, plan Wi-Fi access point locations, patch panels and any fibre runs between floors. Cabling must be installed and tested before move day, not during it.
Publish a comms plan: what happens when, what staff must do (clear desks, back up local files, take laptops home), and who to contact over the move weekend. Notify suppliers, update your registered addresses, and arrange phone number porting or call diverts with your telecoms provider.
The final countdown. Everything now is about removing surprises from move day.
With the groundwork done, move day is about disciplined sequencing rather than heroics.
Shut down in a strict sequence: applications and databases first, then virtual machines, then physical servers, then storage, and network equipment last. Record the order — recommissioning is the exact reverse. Never pull power on a live database server.
Servers and switches travel in anti-static packaging, padded and upright, in a dedicated vehicle — not loose in the back of a furniture lorry. Keep drives and backup media with a named person, and check insurance covers equipment in transit.
At the new site: rack and cable to the plan, power up network equipment first, then storage, then servers, then applications. Verify connectivity, DNS, VPN and line-of-business systems before anyone calls it a night. Then set up desks against the labelled plan.
The move is not finished when the vans leave. The first week in the new office is where small snags are caught before they become real problems.
Start at least eight weeks before your move date, and twelve weeks if you need new leased-line connectivity. Internet circuit lead times are the single most common cause of delay: a new fibre leased line can take 30 to 90 working days to install, and broadband or FTTP typically takes two to four weeks.
Internet connectivity lead times. Everything else about a move can be compressed into a weekend, but a leased line cannot be hurried. Order connectivity for the new premises as the very first action in your plan, and arrange a 4G/5G or broadband backup circuit as a contingency in case the primary line slips.
An office move is often the ideal moment to review this. If servers are approaching end of life, migrating workloads to Microsoft 365, Azure or hosted infrastructure before the move can remove the riskiest part of the relocation entirely. If you keep physical servers, verify backups before the move and plan a strict decommission and recommission order.
Move over a weekend or out of hours, have connectivity and structured cabling live at the new site before move day, take verified backups beforehand, and test every desk, phone and printer before staff arrive. With proper planning, most businesses lose no working time at all.
Dispose of redundant equipment through a licensed WEEE (Waste Electrical and Electronic Equipment) recycler and obtain certificates of data destruction for any drives or devices that held company data. Never skip data-bearing asset destruction — a discarded hard drive is a data breach waiting to happen.
Record Group has been planning and delivering IT relocations and office moves across the West Midlands since 1998 — surveys, cabling, connectivity, weekend moves and 30 days of post-move support included.